Friday, April 10, 2009

No action all week...

We spoke to the Site manager on Tuesday and he assured us that the mess up will be fixed....though it might take some time! An engineering report needs to be done and then the work will be fixed up and then rechecked by the engineer....
Apparently they were going to do the trusses on Tuesday but the crane broke down on site! The brickie that was booked has had to be cancelled... Could this be the start of a nightmare build? It has all gone so well up to now!
We are already a week behind now as nothing has happened this week, add that to the week of rain we have had = 2 weeks behind at the least! And it is meant to rain next week....

1 comment:

  1. Hi
    Its a nice piece of information, it will really helpful for the people who are planning to construct new house. Generally people face lot of problems while shifting an existing house. Its really a difficult task.For all those who hate wasting time My house Removals in Sutton is for you.My house removal provides you man and van services in all over UK.

    ReplyDelete